Task list and timetable for iteration 40

Status

OK/Not Ok

1. Highlights approved

OK

2. Assignment of tasks

OK

3. Task list and time table approved

OK

4. Implementation phase started

OK

5. Release test phase started

OK

6. Assignment phase for next iteration started

OK

7. Iteration 40 completed

Highlights for Iteration

Development procedure

Table of tasks

Tasks for iteration 40. Updated 15. December 2009

Estimate md

Main responsible

Reviewer

Remaining md at 15. December 2009

Comments

Status

Implementation phase (task x-n)

Open Source release + bugs and feature request

Total 3

-

-

Total 3

-

Support of Open Source Release

1. Support of released NetarchiveSuite

2

All (Google calender)

2

Ongoing

2. Implement translateprocess. Adjustment to Open Source partners.

1

CSR

SVC

-

Bugs and Features requests

Prioritized bugs according to list of priority 4 and priority 3 tasks.

Total 5

-

-

SubTotal 0

..

-

Priority 4 bugs

3. Module Access: Bug 1758 UrlCanonicalizerFactory falls back to default value silently

0,5

CSR

SVC

0

High Priority

OK

4. Module Harvester: Bug 1777 Add event seeds only accepts a very short list of seeds

3

SVC

HBK

0

High priority

OK

Priority 3 bugs

5. Module Access: Bug 1796 Configurations manual doesn't include anything about setting up wayback

1

HBK

SVC

0

OK

6. Module Access: Bug 823 No index = Internal server error

7. Module Monitor: Bug 1756 JMX status page does not update when a new application is started on previously used JMX port

8. Module Archive: Bug 1782 Same datetime repeated many times, while logging batch checksum of files

9. Module Documentation: Bug 1779 Improve documentation of the additional tools

10. Module Archive: Bug 1764 Poor information on failed batch job

11. Module Documentation: Bug 1732 LocalArcRepositoryClient not documented

12. Module Archive: Bug 1727 Poor error message in RunBatch

13. Module Archive: Bug 1708 bitpreservation logic offers "add to archive" for file that is not in either location

14. Module Deploy: Bug 1705 Make jmxremote.access writable before overwriting it (install script)

JOLF

SVC

OK

15. Module Archive: Bug 1619 Potential NullPointer exception in RemoveAndGetFileMessage.getData()

16. Module Archive: Bug 1260 Too much and wrong feedback information on "Missing pages"

17. Module Monitor: Bug 1205 Security policy for unit tests contains hardcoded path to development environment

18. Module Archive: Bug 1193 Exceptions from FileBatchJob stop batch job processing

19.

..

Prioritized Feature Requests according to list of priority 4 and priority 3 tasks

Total 21

-

-

SubTotal 21

-

Priority 4 Feature request

20. Module harvester: Feature request 1116 Global crawlertraps

6

CSR

SVC

0

Assignment . See also FR 1120 Review decides whether some of the tasks will be implemented. Backend. To be finished in Iteration 41. Decision: Only assignment.

OK

21. Module harvester: Feature request 1696 Ingest domain seed URLs

5

Nicolas

SVC

0

Postponed

22. Module harvester: Feature request 1688 Monitoring broad crawls.

5

Nicolas

SVC

0

FR under discussion on mailing list.

Postponed

23. Module archive: Feature request 1736 Monitoring batchjobs

2

JOLF

HBK

0

New feature request for restructuring the Batch architecture has been made. This FR only deals with improved logging.

OK.

24. Module monitor: Feature request 1757 Need a way to remove an application from lists of monitored applications

2

HBK

SVC

0

High priority .

OK

Priority 3 Feature request

25.Module Harvester: Feature request 1774 Stop using the JMS queues for queuing snapshot harvests

26. Module Harvester: Feature request 1681 Add seed to DB via webservice (via Browser Extension/Rich Client)

?

Andreas

Started Postponed

27. Module Harvester: Feature request 1682 Statistics (DB access, scripts, batch jobs ....)

?

Andreas

?

28. Module Harvester: Feature request 1683 Util for regenerate admin.data file

?

Andreas

?

29. Module Harvester: Feature request 1684 Activity when domain is to be crawled. One table for seed

?

Andreas

?

30. Module Archive: Feature request 1743 When accessing Bitpreservation this takes really long time

?

Andreas

?

31. Module Harvester: Feature request 1120 Crawlertrap info should be shareable between institutions

?

Andreas

SVC will add comments to this FR. Might be an easy solution to share Crawlertraps by emailing files with crawler trap informations.

Redundant (Copy of 20)

32. Module Harvester: Feature request 1066 Show whether seed URL existed

?

Andreas

?

33. Module Archive: Feature request 1809 Write assignment for improving batchjob interface

?

JOLF

..

34a. Module Harvester: Feature request 1134 Filter job lists by category

?

Nicolas/Sara

..

34b. Module Harvester: Feature request 1668 Paginate and make sortable and searchable the list of jobs

?

Nicolas/Sara

..

Roadmap tasks

Total 52?

-

-

Total 8,5

-

Tasks from ...

35. Review of WARC Tools Phase III SRS

5

SVC

HBK,CSR,TLR

High priority

OK

36. Assignment for enhanced QA tools

2

Postponed

37. Finalize Assigment for Harvester for support of WARC format

?

38. Finalize assignment for Assignment group B.2.2

0,5

39. Implement Assignment B.2.2a - Generalise replica to include all checksum voters

8

JOLF

SVC

0

High priority

OK

40. Implement Assignment B.2.2b - Store bit preservation information in a database

8

In Progress

41. Implement Assignment B.2.3 - Use segments in bitarchives

6

42. Implement Assignment B.2.4 - Write BitPreservation scheduler

5

43. Implement Assignment B.2.5 - Write BitPreservation webinterface

6

44. Finalize assignment for Assignment group B.4.4 - Yet more better infrastructure

2

..

..

Wayback/Nutchwax tasks independent of NetarchiveSuite code-freeze.

Total x

-

-

Total x

-

Tasks from ...

-

45 Evaluation of !NutchWax.

2?

HBK

CSR

High priority

OK

In progress

..

Converting old Web collections to Netarchive.dk. See proposal. These task will be independent of NetarchiveSuite code-freeze.

Total x

-

-

Total x

-

Tasks from ...

46. Investigation in dataformat as well as methods

?

SVC

HBK

In progress

47. Prepare ARC/WARC document for basis of decision to Steering group. Must old data be ingested into Neetarkivet.dk using ARC container or WARC container.

?

HBK

SVC,TLR

High priority

In progress

48. Generic converter prototype

?

HBK

SVC

High priority

.. Done Committed in CVS needs code review

49. Old KB Webarchive

?

SVC

HBK

In progress

50. Old Webarchive harvested with ARC-Httrack

?

HBK

SVC

.. Under dev.

51. Old Webarchive harvested with Wget

?

HBK

SVC

In progress

52. Old Webarchive harvested with NedLib

?

SVC

HBK

In progress

53. Old Webarchive from Niels Brugger in waf format

?

HBK

JOLF

.. Done Waiting for Code Review

54. Old Webarchive from Kurt Vest Nielsen (Ingeniøren from 1995)

?

JOLF

HBK

Postponed

55. Webarchive from the library of The Danish Parliament

?

SVC

HBK

Postponed

56. Old Webarchives from Net-papers

?

SVC

HBK

Postponed

57. Digital publications of The Danish Law Gazette from the missing period

?

SVC

HBK

Postponed

58. Old Webarchive from Niels Brugger collected by HTTrack

?

HBK

SVC

Postponed

59. Prepare ingest of extracted data from Internet Archive into Netarkivet.dk

SVC

HBK

High priority.Output will be a document showing what has been made of choice and an instruction to the daily manager of Netarkivet.dk of how to ingest the data.

In progress

60. Ingest received data from Internet Archive into Netarkivet.dk

CLO

HBK

High priority

Awaiting document from task 59.

Common tasks calculated as implementation tasks

Total x

-

-

Total x

-

Others

Total x

-

-

SubTotal 2

-

61. Setup of new KB test system

2

TLR

SVC

2

High priority

In progress

62. Test of 64 bit version of KB-PROD-ADM

2

TLR

SVC

2

High priority

..

63. Architectual consideration: Move harvesters close to the backbone of the research network.

2

SVC

HBK

2

High priority

..

64. Create/execute a batch test script specified by 1 or 2 researches

2

JOLF

HBK

2

..

65. Prepare joint face to face meeting with UDV and Pligt/Natinal

1

CHH

CSR

1

..

66. Prepare action plan for development activities

1

CHH

CSR

1

High priority

..

67. Status of Crawl-problems (Netarchive.dk)

1

CHH

CSR

1

..

Prepare release test

Total x

-

-

SubTotal 12

-

68. Prepare release test

6

0

OK

Available man-days for implementation phase

Total x

-

-

Total x

-

Release test phase (task ...)

Release test

Total x

-

-

Total 12

-

69. Execute release test.

12

TLR

All

12

In progress

'

..

Release notes

Total x

-

-

Total 0,5

-

70. Write release note

0,5

SVC

Awaiting end of code freeze

Available man-days for release test phase

Total x

-

-

Total 10

-

Assignment phase for next iteration (task ...)

71. Component bug/feature fix/management

QA

..

72. Define goals for Iteration 41 task list

CHH

..

73. Presentation of goals and tasks for Iteration 41. Achieve a common understanding of the purpose of the iteration and each task on status meeting

SVC

..

74. Assignment of tasks, bugs and feature request

QA

..

75. Update release test procedure

TLR

..

Available man-days for assigment phase

Total x

-

-

Total 22

-

Timetable

Timetable iteration 40. Updated 13. November 2009

Start time

End time

Responsible

Baseline 13. November 2009. Start time

Baseline 13. November 2009. End time

1. Implementation of decided tasks

16. November 2009

11. December 2009

16. November 2009

11. December 2009

2. Code freeze. Create the build for release test and notify when build is ready

14. December 2009

SVC

14. December 2009

3. Release test

14. December 2009

16. December 2009

TLR

14. December 2009

16. December 2009

4. Code unfreeze

17. December 2009

SVC

17. December 2009

5. Assignments, bug components and bug fixes

16. December 2009

18. December 2009

16. December 2009

18. December 2009

eration39TaskList here.

Iteration40TaskList (last edited 2010-08-16 10:24:32 by localhost)