Task list and timetable for iteration 35

Status

OK/Not Ok

1. Highlights approved

OK

2. Assignment of tasks

OK

3. Task list and time table approved

OK

4. Implementation phase started

OK

5. Release test phase started

6. Assignment phase for next iteration started

7. Iteration 35 completed

Highlights for Iteration 35

Development procedure

Table of tasks

Tasks for iteration 35. Updated 26 August 2008

Estimate md

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

Remaining md at 21 August 2008

Status

Implementation phase (task 1-22)

Support Open Source + bugs and feature request

Total 33,5

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

Total 12

-

Support of Open Source Release. See also [:UpdateNetarchiveSuiteWiki:decided structure] for wiki

1. [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/SupportNetarchiveSuite Support] of released NetarchiveSuite

2

QA

All (Gforge list)

0,5

0,5

1

2. Simplification of fields in the Gforge bug tracker. Write bug reporting procedure. See [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/ReferatDagsordenIBMaj2008 summary] from joint meeting.

2,5

KFC

ELZI

1,5

1

1

Simplification of tracker fields finalised. Instruction and bug procedure in progress.

3. Implement development structure on wiki

1

ELZI

KFC

1

1

Not started

4. Process description of external patches

2

ELZI

SVC

0,5

1,5

2

Low priority

5. Preparation of tutorials for ECDL 2008

12

KFC

SVC

0

8

0

Essential tutorial features implemented.

Bugs and Features requests

Prioritized bugs according to [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/BugPrioritering19Dec2007 list from December the 19th 2007] '

SubTotal 10

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN md

TLR/ md

SubTotal ?

-

6. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1193 Bug 1193] Exceptions from FileBatchJob stop batch job processing

4

SVC

ELZI

0,5

0,5

1

Update of unit test and codereview is missing

7. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1152 Bug 1152] URLs with { or } not browsable.

2

ELZI

SVC

0,5

1,5

0

Postponed

8. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1157 Bug 1157] jobs disappeared in a strange way

2

ELZI

SVC

0,5

1,5

0,5

Waiting for review. Decide on release test.

9. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=934 Bug 934] could not start harvester due to JMX problem (Adress already in use)

2

SVC

ELZI

1,5

0,5

0

Postponed

10. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1226 Bug 1226] Discrepancy between how our database are defined in the dev, and prod environments respectively. (Requirements: [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1226 Feature request 1252] Upgrade to Apache Derby 10.4.1.3) Decide whether upgrade of Java version is better.

2

ELZI

SVC

1

1

0

Update to Java 1.6 implemented. Update of Derby postponed. Migration of database postponed.

Prioritized Feature Requests according to [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/BugPrioritering19Dec2007 list from December the 19th 2007]

SubTotal 2

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

SubTotal ?

-

11. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1140 Feature request 1140] Count inline material as belonging to the domain it's inlined in.

2

SVC

ELZI

1,5

0,5

0

Postponed

[:Roadmap:Roadmap tasks]. Stable release 3.8.

Total 17

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

Total ?

-

Tasks from defined at[http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/ReferatDagsordenIBMaj2008 joint meeting May the 29th, 2008]

12. Update assignments for [:AssignmentGroupB2:Assignment group B.2] - Improve and isolate bit preservation GUI

4

ELZI

KFC

0

2

2

1

Waiting for review.

13. Update assignments for [:AssignmentGroupB4:Assignment group B.4.4] - Improve batch architecture

1

KFC

ELZI

1

0

Postponed

14. Analyse of the future requirements for index handling. Reference: '[https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1078 Bug 1078] DeDuplikator index too large?

4

SVC

ELZI,TLR

3

1

0

Postponed

15a. Implementation of [http://netarchive.dk/suite/Development/Settingsstructure Settings]

8

ELZI

SVC,KFC

1,5

0,5

5

0

Waiting for review.

15b. Implementation of settings necessitate new deploy. Analyse possibilities and write assignment for new deploy. See [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/ProposalKFC21Aug2008 proposal] from KFC.

2

KFC

ELZI

1,5

0,5

2

Not started

Common tasks calculated as implementation tasks

Total 2

Main responsible

Other participants

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

Total ?

-

16. Update of manuals

1

ELZI

-

0,5

0,5

0

OK. Not yet finalised: Information of new settings structure to CLO for update of user manual.

17. Role management

0,5

-

0,5

0.5

On going

18. Other planned tasks

-

-

-

-

-

-

-

T5 production bug in version 3.6.0

19. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1282 Bug 1282] Reregistering applications every minute seems to overwhelm the GUIApplication and the JMSbroker

2

SVC

KFC

1

1

OK

Release test of patched 3.6.0

20. Prepare [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35Patchrelease patch release test]. (Change of JMS broker setting)

1

KFC

SVC

0,5

0,5

OK

21. Execute [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35Patchrelease patch release test]. Change of JMS broker setting)

2

KFC

ELZI

1,5

0,5

OK

Prepare release test of Iteration 35

22. Prepare [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35ReleaseTest release test].

6

TLR

All

6

2

In progress

Total md implementation phase (Task 1-21)

Total 58

-

-

14

18

20

0

6

Total ?

-

Release test phase (task 20-22)

Release test

Total 9

Main responsible

Other participants

-

-

-

-

-

Total ?

-

23. Execute [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35ReleaseTest release test].

6

TLR

KFC,ELZI,SVC

1

1

1

3

..

24. Component bug/feature fix/management

2,5

QA

KFC,ELZI,SVC

1

0,5

1

..

Release notes

Total 0,5

-

-

SVC/ md

KFC/ md

ELZI/ md

NN/ md

TLR/ md

Total 0,5

-

25. Write [http://netarchive.dk/suite/Release_Overview release notes] for iteration 35

0,5

KFC

ELZI

0,5

-

Total for release test phase

Total 9

-

-

2

2

2

0

3

Total ?

-

Assignment phase for next iteration (task 23-27)

26. Component bug/feature fix/management

1,5

QA '

All

0,5

0,5

0,5

0

Regular process

27. Define goals for [:Iteration36TaskList:Iteration 36 task list.]

0,1

CHH '

KFC

0,1

0

-

28. Presentation of goals and tasks for Iteration 36. Achieve a common understanding of the purpose of the iteration and each task on status meeting

0,1

KFC '

All

0,1

-

29. Assignment of tasks, bugs and feature request

3

CHH '

All

1

1

1

0

Regular process

30. Update release test procedure

TLR '

All

1

Regular process

31. [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/DagsordenIBOktober2008 Joint meeting]

5

CHH

All

1

1

1

1

1

Total md for assigment phase

Total 9

-

-

2

2

2

1

2

Total ?

-

Total md for Iteration 35

Total 76,6

19,5

22,5

22,5

1

11

Detailed timetable

Timetable

Timetable iteration 35. Updated 16-May-2008

Start time

End time

Responsible

Baseline 16 May 2008. Start time '

Baseline 16 May 2008. End time' '

1. Implementation of decided tasks

30-6-2008

25-9-2008

ALL

30-6-2008

25-9-2008

2. Code freeze. Create the build for release test and notify when build is ready

26-9-2008

KFC

26-9-2008

3. Release test

26-9-2008

30-9-2008

TLR

26-9-2008

30-9-2008

4. Code unfreeze

1-10-2008

KFC

1-10-2008

5. Assignments, bug components and bug fixes

1-10-2008

2-10-2008

1-10-2008

2-10-2008