Task list and timetable for iteration 35
Status |
OK/Not Ok |
1. Highlights approved |
|
2. Assignment of tasks |
|
3. Task list and time table approved |
|
4. Implementation phase started |
|
5. Release test phase started |
|
6. Assignment phase for next iteration started |
|
7. Iteration 35 completed |
|
Highlights for Iteration 35
[http://kb-prod-udv-001.kb.dk/twiki/bin/edit/Netarkiv/SupportNetarchiveSuite Support] of released NetarchiveSuite (http://netarchive.dk/suite).
Enhance NetarchiveSuite wiki according to [:UpdateNetarchiveSuiteWiki:decided structure].
Implement following tasks according to [:Roadmap:roadmap "stable release version 3.8"].
Module Archive
- None
Module Harvester
- None
Module Viewer
- None
Module Common
- Simplification of settings
- Bug fixes according to updated prioritized bug list
- Iteration 35 is planned as a developement release candidate.
Development procedure
Implementation according to [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/CurrentUdviklingsMetodik implementation methodology]
- Intensive period of implementation and release test
- Estimated 59 md for implementation.
- Estimated 6 md for release test.
- Estimated 4 md for assignemnt of tasks for iteration 35.
- Target release: Week 40, 2008
Table of tasks
Tasks for iteration 34. Updated 18-June-2008 |
Estimate md |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
Remaining md at 30-June-2008 |
Status |
Implementation phase (task 1-21) |
||||||||||
Support Open Source + bugs and feature request |
Total 31,5 |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
Total ? |
- |
Support of Open Source Release. See also [:UpdateNetarchiveSuiteWiki:decided structure] for wiki |
||||||||||
1. [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/SupportNetarchiveSuite Support] of released NetarchiveSuite |
2 |
QA |
All (Gforge list) |
0.25 |
|
|
|
|
|
|
2. Simplification of Gforge bug tracker fields and bug reporting procedure |
2,5 |
KFC |
ELZI |
|
|
|
|
|
|
|
3. Implement development structure on wiki |
1 |
ELZI |
KFC |
|
|
|
|
|
|
|
4. Process description of external patches |
2 |
ELZI |
SVC |
|
|
|
|
|
|
|
5. Preparation of tutorials for ECDL 2008 |
12 |
KFC |
|
|
|
|
|
|
|
|
Bugs and Features requests |
||||||||||
Prioritized bugs according to [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/BugPrioritering19Dec2007 list from December the 19th 2007] |
SubTotal 10 |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN md |
TLR/ md |
SubTotal 1 |
- |
6. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1193 Bug 1193] Exceptions from FileBatchJob stop batch job processing |
4 |
- |
|
|
|
|
|
|
|
- |
7. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1152 Bug 1152] URLs with { or } not browsable. |
2 |
- |
|
|
|
|
|
|
|
- |
8. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1157 Bug 1157] jobs disappeared in a strange way |
2 |
- |
|
|
|
|
|
|
|
|
9. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=934 Bug 934] could not start harvester due to JMX problem (Adress already in use) |
2 |
- |
|
|
|
|
|
|
|
- |
10. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1226 Bug 1226] Discrepancy between how our database are defined in the dev, and prod environments respectively. (Requirements: [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1226 Feature request 1252] Upgrade to Apache Derby 10.4.1.3) |
2 |
|
|
|
|
|
|
|
|
|
Prioritized Feature Requests according to [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/BugPrioritering19Dec2007 list from December the 19th 2007] |
SubTotal 2 |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
SubTotal 0 |
- |
10. [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1140 Feature request 1140] Count inline material as belonging to the domain it's inlined in. |
2 |
|
|
|
|
|
|
|
0 |
|
[:Roadmap:Roadmap tasks]. Stable release 3.8. |
Total 17 |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
Total 1,5 |
- |
Tasks from defined at[http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/ReferatDagsordenIBMaj2008 joint meeting May the 29th, 2008] |
||||||||||
11. Update assignments for [:AssignmentGroupB2:Assignment group B.2] - Improve and isolate bit preservation GUI |
4 |
|
- |
- |
|
|
|
|
|
- |
12. Update assignments for [:AssignmentGroupB4:Assignment group B.4.4] - Improve batch architecture |
1 |
|
|
|
|
|
|
|
|
- |
13. Analyse of the future requirements for index handling. Reference: [https://gforge.statsbiblioteket.dk/tracker/index.php?func=detail&aid=1078 Bug 1078] DeDuplikator index too large? |
4 |
|
|
|
|
|
|
|
|
- |
14. Implementation of [http://netarchive.dk/suite/Development/Settingsstructure Settings] |
8 |
|
|
|
|
|
|
|
|
|
Common tasks calculated as implementation tasks |
Total 2 |
Main responsible |
Other participants |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
Total 6 |
- |
15. Update of manuals |
1 |
- |
- |
|
|
|
|
|
- |
- |
16. Role management |
1 |
- |
|
|
|
|
|
|
|
- |
18. Other planned tasks |
- |
- |
- |
- |
- |
|
|
|
- |
- |
Prepare release test of Iteration 35 |
||||||||||
21. Prepare [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35ReleaseTest release test]. |
6 |
TLR |
All |
|
|
|
|
6 |
|
- |
Total md implementation phase (Task 1-21) |
Total 56,5 |
- |
- |
9 |
5 |
0 |
2 |
6 |
Total 24 |
- |
Release test phase (task 22-24) |
||||||||||
Release test |
Total 9 |
Main responsible |
Other participants |
- |
- |
- |
- |
- |
Total 9 |
- |
22. Execute [http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/Iteration35ReleaseTest release test]. |
6 |
TLR |
KFC,ELZI,SVC |
1 |
1 |
1 |
|
3 |
6 |
.. |
23. Component bug/feature fix/management |
2,5 |
QA |
KFC,ELZI,SVC |
1 |
0,5 |
1 |
|
|
2,5 |
.. |
Release notes |
Total 0,5 |
- |
- |
SVC/ md |
KFC/ md |
ELZI/ md |
NN/ md |
TLR/ md |
Total 0,5 |
- |
24. Write [http://netarchive.dk/suite/Release_Overview release notes] for iteration 35 |
0,5 |
KFC |
ELZI |
|
0,5 |
|
|
|
0,5 |
- |
Available man-days for release test phase |
Total 9 |
- |
- |
2 |
2 |
2 |
0 |
3 |
Total 9 |
- |
Assignment phase for next iteration (task 16-20) |
||||||||||
25. Component bug/feature fix/management |
2 |
- |
All |
|
|
|
|
|
0 |
Regular process |
26. Define goals for [:Iteration36TaskList:Iteration 36 task list.] |
0,5 |
CHH |
KFC |
|
|
|
|
|
0 |
- |
27. Presentation of goals and tasks for Iteration 36. Achieve a common understanding of the purpose of the iteration and each task on status meeting |
0,1 |
KFC |
All |
|
|
|
|
|
0,1 |
- |
28. Assignment of tasks, bugs and feature request |
0 |
- |
All |
|
|
0 |
0 |
|
0 |
Regular process |
||<style="vertical-align: top;">29. Update release test procedure
|
TLR |
All |
|
|
|
|
1 |
1 |
Regular process |
|
Available man-days for assigment phase |
Total 22 |
- |
- |
0 |
0 |
0 |
0 |
2 |
Total 22 |
- |
Detailed timetable
[http://kb-prod-udv-001.kb.dk/twiki/bin/view/Netarkiv/NumberIBmdJuneSeptember2008 Detailed time table (Not open)]
Timetable
Timetable iteration 35. Updated 16-May-2008 |
Start time |
End time |
Responsible |
Baseline ??'. Start time |
Baseline ??. End time' ' |
1. Implementation of decided tasks |
30-6-2008 |
- |
|
- |
- |
2. Code freeze. Create the build for release test and notify when build is ready |
- |
|
- |
- |
|
3. Release test |
- |
- |
- |
- |
- |
4. Code unfreeze |
- |
|
- |
- |
|
5. Assignments, bug components and bug fixes |
- |
- |
|
- |
- |